Today John and I worked on the closet in Duke. The cabling was routed a little different than the ones before. It had switch at the top going to 3 patch panels one above it and two below it. Then it had two switches at the bottom going to the other patch panels. We rerouted the cables so they are now in a neat order. Once we finished that I confirmed that they were in web help desk.

Before

After

Once that was done Brian had a wireless access point in Bryan Jr. that was down so we went out and test the cable from the switch to the access point. It tested fine. then tested it from where it ran through another closet it still test fine. Brian rerouted the cable then we reinstalled the access point and confirm that it was working correctly.

5.5 Hours